Project 201: Deliverables to be completed in May

This milestone contains all the issues that needs to be completed in May for project 201.

  • Activity 1.1: Review existing implementations, research literature, and internal documentation

    • Deliverables: Review of existing signaling channel library implementations, research literature, and internal documentation.
  • Activity 2.1: Research possible fingerprint diversification system implementations.

    • Deliverables: Review of fingerprint obfuscation system implementations
  • Activity 3.4: Implement AMP Cache in Rust

    • 3.4.1 prototype of ampcache in rust
      • Deliverables: Prototype of AMPCache signaling channel
  • Activity 3.6: Implement SQS in Rust

    • 3.6.1 prototype sqs in rust.
      • Deliverables: Prototype of SQS signaling channel
  • Activity 4.1: Evaluate nine promising signaling channels for use in library.

    • Deliverables: Evaluate nine promising signaling channels for use in the library.
  • Work items 6
  • Merge requests 0
  • Participants 5
  • Labels 1
Loading
Loading
Loading
Loading
100% complete
100%
Start date
May 4, 2026
May 4
-
May 30 2026
Due date
May 30, 2026 (Past due)
6
Work items 6
Open: 0 Closed: 6
None
Total weight
None
0
Merge requests 0
Open: 0 Closed: 0 Merged: 0
0