Milestone 3:
beta release of ooni-probe on m-lab.
beta release of ooni-probe client to users.
streamlined data collection.
progress report to date.
**High Level Meeting Overview: **
Assess immediate situation. Figure out most direct path to deliver. Discuss future tasks and requirements and available resources. Discuss Roger's recent email on the topic.
**Tasks to do during this call: **
-
Discuss strategy/plan for milestone 3:
-
Get the low-down from Andrew
-
Determine OONI beta release date (MLAB)
-
before/after/during Tor Dev Meeting ( ~ 3 weeks from now )?
-
Determine/Agree on the feasible minimum set of tasks
-
Get commitment from developers on availability for next 1<n<=3 weeks
-
Assign names to tickets / Ticket Triage / Push everything else
-
Assign roles to people: who should be responsible for what part of the project.
- Possible roles:
- oonib collector developer
- oonib test helper developer
- ooniprobe test writer
- ooni infrastructure maintainer
- Possible roles:
-
Discuss where we want to be by milestone 4
-
Realize that this is ~ 1 month after Tor dev meeting and bounded by travel.
-
What are we going to deliver by this deadline?
-
Cross platform packaging.
-
GUI, how (tkinter, HTML5/JS)?
-
OONI website
-
Other?
-
Discuss Budget and Hiring
-
Discuss Hiring
-
Set date for next call
Tasks to do to prepare for the call:
-
Collect/Create tickets from user feedback
-
Create tickets for simple test types
-
Examine requirements for MLAB data collection
-
Identify blocking tickets and ticket priority
-
Review emails between MLAB and ooni devs
-
Create a wiki page for notes
-
take a wild stab at triaging/prioritizing tickets
-
Make a setup script to deploy oonib on the m-lab nodes
-
Setup oonib and ooniprobe on some machines offerred by the leap project.
-
Do a better job at documenting what we currently have