= Sponsor O =
|
|
|
== Timeline ==
|
|
|
|
|
|
# Sponsor O
|
|
|
## Timeline
|
|
|
July 2013 - July 2015
|
|
|
|
|
|
== Deliverables ==
|
|
|
'''Tor Instant Messaging Bundle'''
|
|
|
## Deliverables
|
|
|
**Tor Instant Messaging Bundle**
|
|
|
|
|
|
1. Audit the Pidgin chat client, fixing security bugs, and make the Tor Instant Messaging Bundle available to end users.
|
|
|
|
... | ... | @@ -15,11 +15,11 @@ July 2013 - July 2015 |
|
|
|
|
|
4. Implement an automated build and testing infrastructure to produce nightly Tor Messenger builds and automatically test them.
|
|
|
|
|
|
'''Tor Mail Bundle'''
|
|
|
**Tor Mail Bundle**
|
|
|
|
|
|
5. Prototype a Tor Mail Bundle based on Thunderbird and Torbirdy, similar to Tor Browser and Tor Messenger.
|
|
|
|
|
|
'''Help Desk and Documentation Improvement and Localization'''
|
|
|
**Help Desk and Documentation Improvement and Localization**
|
|
|
|
|
|
6. Add Farsi, French, Spanish, and Arabic translators to the help desk staff.
|
|
|
|
... | ... | @@ -33,42 +33,42 @@ July 2013 - July 2015 |
|
|
|
|
|
11. Concentrate efforts on outreach to Iranian end users and potential supporters in the technology community; to include train the trainer sessions, advertising on social networks, and interviews on radio and television stations operated by and for the Iranian diaspora.
|
|
|
|
|
|
'''Hidden Service Usability Improvements'''
|
|
|
**Hidden Service Usability Improvements**
|
|
|
|
|
|
12. Analyze usability challenges with the setup of secure hidden services; use these findings to develop a script and accompanying documentation to further enhance usability for civil society technologists and network security engineers.
|
|
|
|
|
|
== Quarterly Milestones ==
|
|
|
=== Q3/2013 ===
|
|
|
## Quarterly Milestones
|
|
|
### Q3/2013
|
|
|
[[TicketQuery(keywords~=sponsoro201307|sponsoro201308|sponsoro201309,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q4/2013 ===
|
|
|
### Q4/2013
|
|
|
[[TicketQuery(keywords~=sponsoro201310|sponsoro201311|sponsoro201312,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q1/2014 ===
|
|
|
### Q1/2014
|
|
|
[[TicketQuery(keywords~=sponsoro201401|sponsoro201402|sponsoro201403,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q2/2014 ===
|
|
|
### Q2/2014
|
|
|
[[TicketQuery(keywords~=sponsoro201404|sponsoro201405|sponsoro201406,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q3/2014 ===
|
|
|
### Q3/2014
|
|
|
[[TicketQuery(keywords~=sponsoro201407|sponsoro201408|sponsoro201409,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q4/2014 ===
|
|
|
### Q4/2014
|
|
|
[[TicketQuery(keywords~=sponsoro201410|sponsoro201411|sponsoro201412,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q1/2015 ===
|
|
|
### Q1/2015
|
|
|
|
|
|
'''Note: we switched from project tickets to a more informal approach where we keep tasks in a list on this wiki.'''
|
|
|
**Note: we switched from project tickets to a more informal approach where we keep tasks in a list on this wiki.**
|
|
|
|
|
|
[[TicketQuery(keywords~=sponsoro201501|sponsoro201502|sponsoro201503,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Q2/2015 ===
|
|
|
### Q2/2015
|
|
|
[[TicketQuery(keywords~=sponsoro201504|sponsoro201505|sponsoro201506,order=keywords,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Not assigned to a quarter yet ===
|
|
|
### Not assigned to a quarter yet
|
|
|
[[TicketQuery(keywords=SponsorO,type=project,format=table,col=id|summary,row=description)]]
|
|
|
|
|
|
=== Guidelines for Quarterly Milestones ===
|
|
|
### Guidelines for Quarterly Milestones
|
|
|
Important: Please read the following guidelines for project tickets before you create or update a ticket for a quarterly milestone!
|
|
|
|
|
|
1. 20 hours minimum: The task or group of tasks takes at least 20 hours to complete; otherwise, it should be a task/enhancement/defect ticket. Micromanagement considered evil.
|
... | ... | @@ -78,10 +78,10 @@ Important: Please read the following guidelines for project tickets before you c |
|
|
1. Summary: The ticket summary is always an action sentence. "Create project tickets from tasks listed on wiki pages" would be a possible summary, "Project tickets instead of wiki pages" not.
|
|
|
1. Keywords: Project tickets use keywords like "SponsorO20140331" if they're assigned to a quarterly milestone, or just "SponsorO" if they're not assigned yet.
|
|
|
|
|
|
== Tasks ==
|
|
|
## Tasks
|
|
|
[[TicketQuery(keywords~=sponsoro,type!=project,format=table,col=id|summary|keywords|owner|component)]]
|
|
|
|
|
|
=== List of internal deliverables for Q1 and Q2/2015 ===
|
|
|
### List of internal deliverables for Q1 and Q2/2015
|
|
|
1.
|
|
|
|
|
|
* (no tasks left)
|
... | ... | |