Sponsor 28: End of phase 2

There's a few more things we have to do for phase 2 (which ends whenever the PI meeting ends up being in December). Here's a list of the important dates we know about so far:

  • September 14th: RACE 1.5.0 release
  • September 15th: code drop
  • Septeber 23rd: T&E meeting about end of phase test event
  • September 28th: dry run
  • September 30th: images due for end of phase test event
  • October 4th: Test event starts
  • October 25 - 29th: TA2 tests for Georgetown
  • November ??: RACE 1.6.0 release
  • December ??: PI meeting
  • Work items 9