Jan 1, 2022–Mar 31, 2023
Sponsor 28: ONLY PHASE 3 Reliable Anonymous Communication Evading Censors and Repressors (RACECAR)
This is a milestone to track the work needed for phase 3 of sponsor 28.
Many of the dates for this phase are still tentative. List of important dates:
2022
January
- 27: release of RACE v2.0.0
March
- RACE/RiB v2.1.0 release (3 days)
- 31st, T&E meeting
April
- Prepare for scrimmage events: first event of this phase is May 1st. (1 week)
- Prepare for s28 PI meeting: May 2022 (1 week)
May
- 1: T&E test TA2 tests (1 week)
- 11 -13: PI Meeting
June
- RACE real world testing
July
- RACE/RiB v2.2.0 release (3 days)
August
- 24 RACE Phase 3 August 2022 T&E Meeting
September
- 1: T&E Integration tests (1 week)
October
- 1: T&E VoA tests (1 week)
- 1: RACE/RiB v2.5.0 release (3 days)
November
- 1: T&E TA2 tests
December
- 1: PI meeting
- 1: T&E Integration tests (1 week)
2023
January
- 1: T&E VoA tests (1 week)
- 1: RACE/RiB v2.6.0 release (3 days)
February
- 1: T&E TA2 tests (1 week)
- Publish all code and documentation.
- Finish last report.
March
- 1: T&E Integration tests (1 week)