# Costs
|
|
# Costs
|
|
|
|
|
|
|
|
The entire work here should consist of about four weeks of work,
|
|
| Task | Estimate | Certainty | Worst case |
|
|
|
medium uncertainty.
|
|
|-------------------|----------|-----------|------------|
|
|
|
|
| Automation | 20h | extreme | 100h |
|
|
|
|
| Installer changes | 4h | low | 4.4h |
|
|
|
|
| Batch 1 | 20h | low | 22h |
|
|
|
|
| Batch 2 | 60h | medium | 90h |
|
|
|
|
| Batch 3 | 20h | high | 40h |
|
|
|
|
| Cleanup | 20h | medium | 30h |
|
|
|
|
| **Total** | 144h | ~high | ~286h |
|
|
|
|
|
|
|
|
The entire work here should consist of over 140 hours of work, or 18
|
|
|
|
days, or about 4 weeks full time. Worst case doubles that.
|
|
|
|
|
|
|
|
The above is done in "hours" because that's how we estimated batches
|
|
|
|
in the past, but here's an estimate that's based on the [Kaplan-Moss
|
|
|
|
estimation technique][].
|
|
|
|
|
|
|
|
[Kaplan-Moss estimation technique]: https://jacobian.org/2021/may/25/my-estimation-technique/
|
|
|
|
|
|
|
|
| Task | Estimate | Certainty | Worst case |
|
|
|
|
|-------------------|----------|-----------|------------|
|
|
|
|
| Automation | 3d | extreme | 15d |
|
|
|
|
| Installer changes | 1d | low | 1.1d |
|
|
|
|
| Batch 1 | 3d | low | 3.3d |
|
|
|
|
| Batch 2 | 10d | medium | 20d |
|
|
|
|
| Batch 3 | 3d | high | 6d |
|
|
|
|
| Cleanup | 3d | medium | 4.5d |
|
|
|
|
| **Total** | 23d | ~high | ~50d |
|
|
|
|
|
|
|
|
This is *roughly* equivalent, if a little higher (23 days instead of
|
|
|
|
18), for exmaple.
|
|
|
|
|
|
|
|
It should be noted that automation is not expected to drastically
|
|
|
|
reduce the total time spent in batches (currently 16 days or 100
|
|
|
|
hours). The main goal of automation is more to reduce the likelyhood
|
|
|
|
of catastrophic errors, and make it easier to share our upgrade
|
|
|
|
procedure with the world. We're still hoping to reduce the time spent
|
|
|
|
in batches, hopefully by 10-20%, which would bring the total number of
|
|
|
|
days across batches from 16 days to 14d, or from 100 h to 80 hours.
|
|
|
|
|
|
|
|
# Approvals required
|
|
# Approvals required
|
|
|
|
|
|
| ... | |
... | |
| ... | | ... | |