@@ -1571,7 +1571,7 @@ first estimate each task's complexity:

[Kaplan-Moss estimation technique]: https://jacobian.org/2021/may/25/my-estimation-technique/

## Phase A: emergency Icinga retirement
## Phase A: emergency Icinga retirement (4-6 weeks)

| Task                                 | Estimate | Uncertainty | Total (days) |
|--------------------------------------|----------|-------------|--------------|
@@ -1583,7 +1583,7 @@ first estimate each task's complexity:
| karma dashboard                      | 3 days   | moderate    | 4.5          |
| **Total**                            | 4 weeks  | moderate    | 27.5         |

## Phase B: merging servers, more exporters
## Phase B: merging servers, more exporters (5-9 weeks)

| Task                          | Estimate | Uncertainty | Total (days) | Note                           |
|-------------------------------|----------|-------------|--------------|--------------------------------|
@@ -1595,7 +1595,7 @@ first estimate each task's complexity:
| port NRPE checks to Fabric    | 2 weeks  | high        | 20           | could be broken down by check  |
| **Total**                     | 5 weeks  | ~high       | 45           |                                |

## Phase C: high availability, long term metrics, other exporters
## Phase C: high availability, long term metrics, other exporters (10-17 weeks)

| Task                  | Estimate  | Uncertainty | Total (days) | Note                 |
|-----------------------|-----------|-------------|--------------|----------------------|