This page describes the mid-term plan for the TPA/Web team in the
|
|
|
year 2022. The previous [2021 roadmap](roadmap/2021) was built in a mostly ad-hoc
|
|
|
fashion, but we have tried to use the [OKR](https://en.wikipedia.org/wiki/OKR) system to establish
|
|
|
broader goals as well.
|
|
|
|
|
|
The objectives here asset for the first 6 months (or two quarters,
|
|
|
Q1/Q2) of 2022. They will be reviewed quarterly and a new set will be
|
|
|
generated for Q3/Q4.
|
|
|
|
|
|
Note that those OKRs are complementary to the main [TPA roadmap](https://gitlab.torproject.org/tpo/tpa/team/-/wikis/roadmap/2022),
|
|
|
in the sense that the same team is split over both OKRs.
|
|
|
|
|
|
# 2022 Q1/Q2 web OKRs
|
|
|
|
|
|
* OKR: make the donate page easier to maintain and have it support
|
|
|
.onion donations ([milestone 22][])
|
|
|
* [new lektor frontend][]
|
|
|
* [vanilla JS rewrite][]
|
|
|
* [we can donate through the .onion][]
|
|
|
* OKR: make it easier for translators to contribute (almost done! not
|
|
|
ambitious enough?)
|
|
|
* translators can find their own copy of the website without help
|
|
|
* bring build time to 15 minutes to accelerate feedback to
|
|
|
translators
|
|
|
* allow the web team to trigger manual builds for reviews
|
|
|
* OKR: improve documentation across the organization
|
|
|
* [launch dev.tpo][] (Q2)
|
|
|
* "Remove outdated documentation from the header", stop pointing to
|
|
|
dead docs
|
|
|
* we have a plan to fix the wiki situation so that people can find
|
|
|
and search documentation easily
|
|
|
|
|
|
[milestone 22]: https://gitlab.torproject.org/groups/tpo/-/milestones/22
|
|
|
[new lektor frontend]: https://gitlab.torproject.org/tpo/web/donate-static/-/issues/37
|
|
|
[we can donate through the .onion]: https://gitlab.torproject.org/tpo/web/donate-static/-/issues/36
|
|
|
[vanilla JS rewrite]: https://gitlab.torproject.org/tpo/web/donate-static/-/issues/45
|
|
|
[launch dev.tpo]: https://gitlab.torproject.org/tpo/web/dev/-/issues/6
|
|
|
|
|
|
## Progress update, end of January 2022
|
|
|
|
|
|
The translation CI work is already going steadily and could be finished
|
|
|
in early Q1.
|
|
|
|
|
|
We are probably going to keep prioritizing the donate page changes
|
|
|
because if we postpone, it will be more work as updates are still
|
|
|
happening on the current site, which means more rebasing to keep things
|
|
|
in sync.
|
|
|
|
|
|
We observed that some of those tasks are already done, so we may need to
|
|
|
think more on the longer term. On the other hand, we have a lot of work
|
|
|
to be done on the TPA side of things, so no human cycles will be wasted.
|
|
|
|
|
|
# Things that need to happen regardless of the OKRs
|
|
|
|
|
|
We have identified some things that need to happen, regardless of the
|
|
|
objectives.
|
|
|
|
|
|
This key result, for example, was part of the "documentation" OKR, but
|
|
|
seemed relevant to all teams anyways:
|
|
|
|
|
|
* teams have less than 20 tickets across the three lists (backlog,
|
|
|
next, doing), almost zero open (untriaged) tickets
|
|
|
|
|
|
We also need to support those people as part of sponsored work:
|
|
|
|
|
|
* s9 usability - Q1/Q2
|
|
|
|
|
|
* support web maintaince based on the UX feedback
|
|
|
|
|
|
* Work on torproject.org usabilty issues based on user feedback
|
|
|
|
|
|
* Work on community.torproject.org usabilty issues based on user
|
|
|
feedback
|
|
|
|
|
|
* Work on dev.torproject.org usabilty issues based on user feedback
|
|
|
|
|
|
* phase 6 may bring more TPA work but we need to make the schedule
|
|
|
for it with TPA
|
|
|
|
|
|
* s30 - anti-censorship - Q1
|
|
|
|
|
|
* bridges.torproject.org - Q1
|
|
|
|
|
|
* s61 network performance - whole year
|
|
|
|
|
|
* support the work on network simulation
|
|
|
|
|
|
* s96 - china censorship - whole year
|
|
|
|
|
|
* support snowflake scaling
|
|
|
|
|
|
* support rdsys deployment
|
|
|
|
|
|
* support moat distribution
|
|
|
|
|
|
* support HTTP PT creation
|
|
|
|
|
|
* support monitoring bridge health
|
|
|
|
|
|
* support creation and publication of documentation
|
|
|
|
|
|
* support localization
|
|
|
|
|
|
* s123 - USAGM sites - Q1/Q2
|
|
|
|
|
|
* support the project on onion sites deployments
|
|
|
|
|
|
* most of the work will be from February to April/May
|
|
|
|
|
|
* new onion SRE and community person starting in February
|
|
|
|
|
|
|
|
|
Non-web stuff:
|
|
|
|
|
|
* resurrect bridge port scan
|
|
|
* do not scan private IP blocks: kez talked with cohosh/meskio to get
|
|
|
it fixed, they're okay if kez takes maintainership
|
|
|
* make it pretty: done
|
|
|
|
|
|
Some things were postponed altogether:
|
|
|
|
|
|
* decide if we switch to Weblate is postponed to Q3/Q4, as we have
|
|
|
funding then |