Oct 2, 2024–Jan 15, 2025
TPA-RFC-71: emergency email deployments, phase B
Excerpts from TPA-RFC-71:
The proposed solution is:
Timeline
Optimistic timeline
- Late September (W39): issue raised again, proposal drafted (now)
- October:
- W40: proposal approved, installing new rewriting server
- W41: rewriting server deployment, new mailman 3 server
- W42: mailman 3 mailing list conversion tests, users required for testing
- W43: mailman 2 retirement, mailman 3 in production
- W44: Schleuder mailing list migration
- November:
- W45:
eugeni
upgradeWorst case scenario
- Late September (W39): issue raised again, proposal drafted (now)
- October:
- W40: proposal approved, installing new rewriting server
- W41-44: difficult rewriting server deployment
- November:
- W44-W48: difficult mailman 3 mailing list conversion and testing
- December:
- W49: Schleuder mailing list migration vetoed, Schleuder stays on
eugeni
- W50-W51:
eugeni
upgrade postponed to 2025- January 2025:
- W3:
eugeni
upgrade