......@@ -506,19 +506,18 @@ process follows the [Kaplan-Moss estimation technique][].
[actual changes section]: #actual-changes
[Kaplan-Moss estimation technique]: https://jacobian.org/2021/may/25/my-estimation-technique/
| Task | Estimate | Uncertainty | Note | Total (days) |
|----------------------------|----------|-------------|-----------------------------------------------|--------------|
| 1. e2e deliver. checks | 3 days | medium | access to other providers uncertain | 4.5 |
| 2. DMARC reports | 1 week | high | needs research | 10 |
| 3. DKIM signing | 3 days | medium | expiration policy and per-user keys uncertain | 4.5 |
| 4. IMAP deployment | 2 weeks | high | may require training to onboard users | 20 |
| 5. SPF/DMARC records | 3 days | high | impact on forwards unclear, SRS | 7 |
| 6. incoming mail filtering | 1 weeks | high | needs research | 10 |
| 7. new MX | 1 weeks | high | key part of eugeni, might be hard | 10 |
| 8. new mail relays | 3 days | low | similar to current submission server | 3.3 |
| 9. Puppet refactoring | 1 weeks | high | | 10 |
|----------------------------|----------|-------------|-----------------------------------------------|--------------|
| Total | 8 weeks | high | | 80 |
| Task | Estimate | Uncertainty | Note | Total (days) |
|----------------------------|-------------|-------------|-----------------------------------------------|--------------|
| 1. e2e deliver. checks | 3 days | medium | access to other providers uncertain | 4.5 |
| 2. DMARC reports | 1 week | high | needs research | 10 |
| 3. DKIM signing | 3 days | medium | expiration policy and per-user keys uncertain | 4.5 |
| 4. IMAP deployment | 2 weeks | high | may require training to onboard users | 20 |
| 5. SPF/DMARC records | 3 days | high | impact on forwards unclear, SRS | 7 |
| 6. incoming mail filtering | 1 weeks | high | needs research | 10 |
| 7. new MX | 1 weeks | high | key part of eugeni, might be hard | 10 |
| 8. new mail relays | 3 days | low | similar to current submission server | 3.3 |
| 9. Puppet refactoring | 1 weeks | high | | 10 |
| **Total** | **8 weeks** | **high** | | **80** |
This amounts to a total estimate time of 80 days, or about 16 weeks or
four months, full time. At 50EUR/hr, that's about 32,000EUR of work.
......