Action Items
- onboard new people in the project for the "cost-extension" phase.
- release engineering discussion (between cyberta and applications team) about building.
Notes
- Timeline
- Contract with leap until July 2025
- MVP will be ready at the end of June 2024
- User Research: designing the testing framework.
- O1.5: Create and translate download page, user manual and user support materials for launching the Tor VPN client to the world.
- O1.6: Conduct marketing research and execute communication strategy for launching the Tor VPN client to the world.
- Audit on August 2024 for the first part of the project.
- @bella will start managing the project in June.